Стр. 2
Страницы: | Стр.1 | Стр.2 | Стр.3 | Стр.4 |
+------------+-------+--------+--------+--------+--------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦ свайные ¦872,914¦1369,984¦1258,282¦1873,041¦ ¦ ¦ ¦ ¦ ¦ 987,342¦763,527¦1340,226¦ ¦1886,844¦
¦ работы, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ устройство ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ опор ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+--------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦ пролетные ¦872,914¦1347,960¦1154,967¦1805,949¦ ¦ ¦ ¦ ¦ ¦1001,807¦827,509¦1334,068¦ ¦1882,534¦
¦ строения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+--------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦ мостовое ¦872,914¦1439,436¦1206,142¦1911,015¦ ¦ ¦ ¦ ¦ ¦ 964,689¦728,218¦1294,713¦ ¦1506,627¦
¦ полотно ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+--------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦ прочие ¦872,914¦1585,305¦1771,697¦1794,003¦ ¦ ¦ ¦ ¦ ¦ 984,621¦670,899¦1369,775¦ ¦1287,782¦
¦ работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+--------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦Содержание ¦872,914¦1539,673¦1003,404¦1766,844¦ ¦ ¦ ¦ ¦ ¦ 979,856¦712,993¦ ¦ ¦1242,074¦
¦автомобиль- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ных дорог ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦и мостов ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦------------+-------+--------+--------+--------+--------+-------+--------+--------+--------+--------+-------+--------+------+---------
Витебская область (КУП "Витебскоблдорстрой")
-------------+-----------------------------------------------------------------------------+----------------------------------------¬
¦Виды работ ¦Для расчета по ЕР-91 ¦Для расчета по ресурсно-сметным нормам ¦
¦ +-----------------------------------------------------------------------------+----------------------------------------+
¦ ¦Наименование затрат ¦Наименование затрат ¦
¦ +-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ ¦Основ- ¦Эксплу- ¦Строи- ¦Транс- ¦Наклад-¦Плано- ¦Времен- ¦Зимнее ¦СМР ¦Наклад-¦Плано- ¦Времен- ¦Зимнее¦СМР ¦
¦ ¦ная ¦атация ¦тельные ¦портные ¦ные ¦вые ¦ные ¦удоро- ¦(спра- ¦ные ¦вые ¦ные ¦удоро-¦(спра- ¦
¦ ¦зара- ¦машин и ¦матери- ¦затраты ¦расходы¦накоп- ¦здания и¦жание ¦вочно) ¦расходы¦накоп- ¦здания и¦жание ¦вочно) ¦
¦ ¦ботная ¦меха- ¦алы ¦ ¦ ¦ления ¦соору- ¦ ¦ ¦ ¦ления ¦соору- ¦ ¦ ¦
¦ ¦плата ¦низмов ¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Подготови- ¦872,914¦1622,705¦ 878,053¦1736,406¦ ¦ ¦ ¦ ¦ ¦920,443¦693,034¦1140,562¦ ¦ 978,513¦
¦тельные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Земляные ¦872,914¦1750,080¦ 915,515¦1820,598¦887,110¦728,256¦1249,926¦1150,489¦1138,125¦875,321¦654,114¦1230,292¦ ¦1191,994¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Укрепитель- ¦872,914¦1450,548¦1063,110¦1746,757¦864,226¦707,128¦1256,540¦1154,493¦1229,017¦903,072¦713,341¦1200,863¦ ¦1486,083¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦с камнем ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Укрепитель- ¦872,914¦1355,267¦ 833,451¦1723,395¦ ¦ ¦ ¦ ¦ ¦825,504¦650,228¦1214,983¦ ¦1019,041¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦без камня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Искусствен- ¦872,914¦1567,914¦1311,257¦1824,951¦ ¦ ¦ ¦ ¦ ¦912,643¦725,971¦1256,140¦ ¦1704,921¦
¦ные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦сооружения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Основание ¦872,914¦1358,155¦ 948,265¦1816,444¦ ¦ ¦ ¦ ¦ ¦921,126¦757,061¦1221,642¦ ¦1650,489¦
¦из песка, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦песчано- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦гравийной ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦смеси, щебня¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Покрытие из ¦872,914¦1486,287¦1214,285¦1805,247¦ ¦ ¦ ¦ ¦ ¦885,394¦757,419¦1221,353¦ ¦1944,619¦
¦гравийно- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦эмульсион- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ной смеси ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Покрытие из ¦872,914¦1512,946¦1230,785¦1865,665¦ ¦ ¦ ¦ ¦ ¦980,482¦759,969¦1303,707¦ ¦2767,859¦
¦асфальто- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦бетонных ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦смесей ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Фрезерование¦872,914¦1356,411¦ 941,924¦1686,200¦ ¦ ¦ ¦ ¦ ¦900,241¦757,359¦1111,084¦ ¦1133,703¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Разметка ¦872,914¦1359,724¦1151,497¦1744,444¦ ¦ ¦ ¦ ¦ ¦908,796¦731,447¦1259,026¦ ¦1404,661¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Обстановка ¦872,914¦1367,930¦1161,389¦1754,907¦ ¦ ¦ ¦ ¦ ¦844,559¦759,506¦1258,706¦ ¦1253,405¦
¦дороги: ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦установка ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦знаков ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Обстановка ¦872,914¦1602,500¦1338,471¦1732,912¦ ¦ ¦ ¦ ¦ ¦868,329¦703,398¦1269,462¦ ¦1452,726¦
¦дороги: ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦прочие ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Барьерное ¦872,914¦1516,107¦1280,797¦1734,444¦ ¦ ¦ ¦ ¦ ¦954,475¦782,309¦1265,334¦ ¦2833,479¦
¦ограждение ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Работы на ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦мостах, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦в том числе:¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ свайные ¦872,914¦1362,415¦1269,506¦1766,295¦848,076¦787,765¦1313,126¦1281,637¦1436,156¦882,640¦749,469¦1339,682¦ ¦1576,352¦
¦ работы, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ устройство ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ опор ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ пролетные ¦872,914¦1343,039¦1179,366¦1768,380¦ ¦ ¦ ¦ ¦ ¦871,858¦770,057¦1274,566¦ ¦1694,650¦
¦ строения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ мостовое ¦872,914¦1365,292¦1159,657¦1713,010¦876,890¦723,623¦1299,038¦1218,889¦1409,903¦887,372¦709,633¦1304,033¦ ¦1354,216¦
¦ полотно ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ прочие ¦872,914¦1558,970¦1351,178¦1823,242¦882,036¦727,355¦1313,930¦1205,889¦1311,446¦892,043¦732,169¦1304,974¦ ¦1526,926¦
¦ работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Содержание ¦872,914¦1672,748¦ 933,650¦1707,312¦ ¦ ¦ ¦ ¦ ¦881,739¦714,921¦ ¦ ¦1231,669¦
¦автомобиль- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ных дорог ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦и мостов ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+---------
Гомельская область (РУП "Гомельавтодор")
-------------+-----------------------------------------------------------------------------+-----------------------------------------¬
¦Виды работ ¦Для расчета по ЕР-91 ¦Для расчета по ресурсно-сметным нормам ¦
¦ +-----------------------------------------------------------------------------+-----------------------------------------+
¦ ¦Наименование затрат ¦Наименование затрат ¦
¦ +-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦ ¦Основ- ¦Эксплу- ¦Строи- ¦Транс- ¦Наклад-¦Плано- ¦Времен- ¦Зимнее ¦СМР ¦Наклад-¦ Плано- ¦Времен- ¦Зимнее¦СМР ¦
¦ ¦ная ¦атация ¦тельные ¦портные ¦ные ¦вые ¦ные ¦удоро- ¦(спра- ¦ные ¦ вые ¦ные ¦удоро-¦(спра- ¦
¦ ¦зара- ¦машин и ¦матери- ¦затраты ¦расходы¦накоп- ¦здания и¦жание ¦вочно) ¦расходы¦ накоп- ¦здания и¦жание ¦вочно) ¦
¦ ¦ботная ¦меха- ¦алы ¦ ¦ ¦ления ¦соору- ¦ ¦ ¦ ¦ ления ¦соору- ¦ ¦ ¦
¦ ¦плата ¦низмов ¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦Подготови- ¦872,914¦1466,945¦ 965,602¦1727,732¦718,063¦598,113¦1043,681¦1015,922¦1027,801¦729,579¦ 617,378¦1039,761¦ ¦1099,306¦
¦тельные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦Земляные ¦872,914¦1632,877¦ 715,648¦1690,817¦837,271¦717,913¦1259,615¦1254,388¦1367,997¦868,445¦ 740,291¦1245,553¦ ¦1401,742¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦Укрепитель- ¦872,914¦1392,787¦ 951,966¦1724,011¦798,741¦666,552¦1259,076¦1252,986¦1514,969¦814,743¦ 672,073¦1251,145¦ ¦1507,689¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦с камнем ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦Укрепитель- ¦872,914¦1343,612¦1014,466¦1685,220¦851,210¦757,491¦1267,763¦1169,987¦1077,424¦872,902¦ 769,631¦1261,450¦ ¦1079,422¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦без камня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦Искусствен- ¦872,914¦1520,424¦1215,090¦1745,563¦849,360¦721,125¦1241,559¦1229,487¦1757,045¦963,207¦ 783,965¦1230,422¦ ¦1819,758¦
¦ные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦сооружения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦Основание ¦872,914¦1442,312¦ 957,070¦1793,939¦841,333¦636,707¦1335,436¦1340,576¦1858,800¦846,456¦ 743,520¦1331,074¦ ¦1859,412¦
¦из песка, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ПГС, щебня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦Покрытие из ¦872,914¦1540,812¦1276,142¦1939,572¦912,694¦717,646¦1319,265¦1221,805¦2492,921¦922,155¦ 735,996¦1304,983¦ ¦2507,558¦
¦асфальто- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦бетона ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦Фрезерование¦872,914¦1475,689¦ 878,350¦1738,050¦ ¦ ¦ ¦ ¦ ¦912,148¦ 879,460¦1211,067¦ ¦1195,494¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦Ремонт ¦872,914¦1537,808¦1225,698¦1719,568¦ ¦ ¦ ¦ ¦ ¦930,202¦ 849,292¦1348,449¦ ¦1416,893¦
¦покрытия ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦Разметка ¦872,914¦1374,814¦1192,414¦1678,780¦799,592¦718,036¦1248,766¦1117,768¦1687,470¦804,959¦ 724,203¦1243,100¦ ¦1707,921¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦Обстановка: ¦872,914¦1421,036¦1550,325¦1671,590¦866,399¦658,387¦1288,041¦1212,220¦1684,890¦873,725¦ 670,237¦1285,165¦ ¦1778,441¦
¦установка ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦знаков ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦Обстановка: ¦872,914¦1395,916¦1182,874¦1716,887¦832,359¦709,640¦1133,026¦1117,430¦1672,652¦846,888¦ 717,720¦1131,534¦ ¦1455,421¦
¦прочие ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦Барьерное ¦872,914¦1403,655¦1511,881¦1687,914¦843,689¦717,863¦1308,203¦1327,496¦2109,823¦841,603¦ 733,882¦1290,226¦ ¦2132,040¦
¦ограждение ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦Работы на ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦мостах, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦в том числе:¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦ свайные ¦872,914¦1463,698¦1391,083¦1679,360¦957,116¦784,928¦1420,045¦1238,322¦1661,879¦964,128¦ 791,247¦1413,558¦ ¦1762,620¦
¦ работы, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ устройство ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ опор ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦ пролетные ¦872,914¦1382,699¦1393,025¦1724,187¦852,442¦993,991¦1284,499¦1266,497¦1527,209¦863,416¦1002,230¦1279,581¦ ¦1643,173¦
¦ строения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦ мостовое ¦872,914¦1399,415¦1366,604¦1745,024¦819,636¦674,642¦1328,971¦1250,542¦1662,734¦831,727¦ 679,602¦1319,301¦ ¦1746,385¦
¦ полотно ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦ прочие ¦872,914¦1431,222¦1373,448¦1736,428¦909,348¦700,834¦1247,295¦1204,747¦1731,373¦909,233¦ 709,292¦1241,479¦ ¦1779,964¦
¦ работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+--------+
¦Содержание ¦872,914¦1508,645¦1318,598¦1721,376¦ ¦ ¦ ¦ ¦ ¦979,910¦ 587,152¦ ¦ ¦1119,608¦
¦автомобиль- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ных дорог ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦и мостов ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+--------+--------+------+---------
Гомельская область (КПРСУП "Гомельоблдорстрой")
-------------+-----------------------------------------------------------------------------+-----------------------------------------¬
¦Виды работ ¦Для расчета по ЕР-91 ¦Для расчета по ресурсно-сметным нормам ¦
¦ +-----------------------------------------------------------------------------+-----------------------------------------+
¦ ¦Наименование затрат ¦Наименование затрат ¦
¦ +-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦ ¦Основ- ¦Эксплу- ¦Строи- ¦Транс- ¦Наклад-¦Плано- ¦Времен- ¦Зимнее ¦СМР ¦Наклад- ¦Плано- ¦Времен- ¦Зимнее¦СМР ¦
¦ ¦ная ¦атация ¦тельные ¦портные ¦ные ¦вые ¦ные ¦удоро- ¦(спра- ¦ные ¦вые ¦ные ¦удоро-¦(спра- ¦
¦ ¦зара- ¦машин и ¦матери- ¦затраты ¦расходы¦накоп- ¦здания и¦жание ¦вочно) ¦расходы ¦накоп- ¦здания и¦жание ¦вочно) ¦
¦ ¦ботная ¦меха- ¦алы ¦ ¦ ¦ления ¦соору- ¦ ¦ ¦ ¦ления ¦соору- ¦ ¦ ¦
¦ ¦плата ¦низмов ¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦Подготови- ¦872,914¦1371,465¦ 968,436¦1698,536¦ ¦ ¦ ¦ ¦ ¦ 767,127¦673,508¦1198,608¦ ¦1079,696¦
¦тельные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦Земляные ¦872,914¦1727,059¦ 729,776¦1718,036¦848,711¦727,600¦1259,015¦1334,171¦1319,919¦ 859,415¦734,682¦1248,476¦ ¦1338,888¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦Укрепитель- ¦872,914¦1377,088¦ 981,724¦1730,424¦788,583¦618,279¦1290,847¦1244,721¦1401,082¦ 799,043¦633,040¦1286,512¦ ¦1448,816¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦с камнем ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦Укрепитель- ¦872,914¦1384,122¦ 850,459¦1638,009¦945,834¦650,406¦1282,663¦1219,649¦1082,642¦ 951,774¦658,599¦1274,562¦ ¦1097,251¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦без камня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦Искусствен- ¦872,914¦1366,412¦ 927,675¦1801,662¦ ¦ ¦ ¦ ¦ ¦ 938,689¦801,646¦1295,169¦ ¦1867,436¦
¦ные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦сооружения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦Основание ¦872,914¦1360,541¦1207,523¦1809,813¦ ¦ ¦ ¦ ¦ ¦ 950,806¦749,817¦1293,956¦ ¦1628,930¦
¦из песка, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ПГС, щебня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦Покрытие из ¦872,914¦1540,842¦1265,978¦1953,604¦973,586¦910,248¦1409,091¦1245,117¦2567,644¦1005,392¦927,835¦1401,170¦ ¦2582,167¦
¦асфальто- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦бетона ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦Фрезерование¦872,914¦1477,123¦1130,423¦1675,892¦ ¦ ¦ ¦ ¦ ¦ 910,942¦782,655¦1351,970¦ ¦1275,218¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦Ремонт ¦872,914¦1531,098¦1222,147¦1718,089¦ ¦ ¦ ¦ ¦ ¦ 929,340¦847,923¦1345,837¦ ¦1317,632¦
¦покрытия ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦Разметка ¦872,914¦1559,631¦1138,120¦1718,780¦ ¦ ¦ ¦ ¦ ¦ 909,275¦684,428¦1361,367¦ ¦1802,934¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦Обстановка: ¦872,914¦1471,642¦1366,669¦1739,319¦ ¦ ¦ ¦ ¦ ¦ 956,770¦793,079¦1357,986¦ ¦1759,032¦
¦установка ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦знаков ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦Обстановка: ¦872,914¦1469,542¦1184,948¦1732,370¦ ¦ ¦ ¦ ¦ ¦ 929,705¦856,453¦1233,543¦ ¦1672,380¦
¦прочие ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦Барьерное ¦872,914¦1387,225¦1499,885¦1687,092¦ ¦ ¦ ¦ ¦ ¦ 796,839¦684,638¦1336,248¦ ¦2234,332¦
¦ограждение ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦Работы на ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦мостах, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦в том числе:¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦ свайные ¦872,914¦1431,689¦1386,054¦1671,693¦924,499¦712,273¦1254,714¦1205,112¦1637,238¦ 928,440¦718,363¦1251,341¦ ¦1655,942¦
¦ работы, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ устройство ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ опор ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦ пролетные ¦872,914¦1388,613¦1275,058¦1697,598¦957,550¦742,012¦1247,050¦1238,485¦1782,129¦ 959,457¦749,117¦1244,668¦ ¦1789,825¦
¦ строения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦ мостовое ¦872,914¦1472,333¦1273,664¦1729,872¦919,230¦840,298¦1217,402¦1170,407¦1665,514¦ 928,820¦854,286¦1211,134¦ ¦1715,271¦
¦ полотно ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦ прочие ¦872,914¦1571,345¦1419,085¦1723,748¦894,346¦625,331¦1321,394¦1235,841¦1548,919¦ 898,136¦652,416¦1314,944¦ ¦1560,998¦
¦ работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+--------+
¦Содержание ¦872,914¦1482,645¦1281,767¦1726,210¦ ¦ ¦ ¦ ¦ ¦ 909,311¦567,071¦ ¦ ¦1194,748¦
¦автомобиль- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ных дорог ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦и мостов ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦------------+-------+--------+--------+--------+-------+-------+--------+--------+--------+--------+-------+--------+------+---------
Гродненская область (РУП "Гродноавтодор")
-------------+----------------------------------------------------------------------+-----------------------------------------¬
¦Виды работ ¦Для расчета по ЕР-91 ¦Для расчета по ресурсно-сметным нормам ¦
¦ +----------------------------------------------------------------------+-----------------------------------------+
¦ ¦Наименование затрат ¦Наименование затрат ¦
¦ +-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦ ¦Основ- ¦Эксплу- ¦Строи- ¦Транс- ¦Наклад-¦Плано-¦Вре- ¦Зимнее¦СМР ¦Наклад- ¦Плано- ¦Времен- ¦Зимнее¦СМР ¦
¦ ¦ная ¦атация ¦тельные ¦портные ¦ные ¦вые ¦менные¦удоро-¦(спра-¦ные ¦вые ¦ные ¦удоро-¦(спра- ¦
¦ ¦зара- ¦машин и ¦матери- ¦затраты ¦расходы¦накоп-¦здания¦жание ¦вочно)¦расходы ¦накоп- ¦здания и¦жание ¦вочно) ¦
¦ ¦ботная ¦меха- ¦алы ¦ ¦ ¦ления ¦и ¦ ¦ ¦ ¦ления ¦соору- ¦ ¦ ¦
¦ ¦плата ¦низмов ¦ ¦ ¦ ¦ ¦соору-¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦
¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Подготови- ¦872,914¦1588,267¦ 879,942¦1716,735¦ ¦ ¦ ¦ ¦ ¦ 941,432¦672,313¦1214,135¦ ¦ 987,073¦
¦тельные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Земляные ¦872,914¦1592,049¦ 923,887¦1712,901¦ ¦ ¦ ¦ ¦ ¦ 969,029¦806,091¦1338,439¦ ¦1195,512¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Укрепитель- ¦872,914¦1370,888¦1015,972¦1753,521¦ ¦ ¦ ¦ ¦ ¦ 962,336¦723,673¦1207,192¦ ¦1478,900¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦с камнем ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Укрепитель- ¦872,914¦1368,313¦ 867,084¦1714,435¦ ¦ ¦ ¦ ¦ ¦ 920,329¦640,160¦1168,109¦ ¦ 997,090¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦без камня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Искусствен- ¦872,914¦1367,004¦1286,674¦1730,584¦ ¦ ¦ ¦ ¦ ¦ 944,305¦870,848¦1417,481¦ ¦1594,734¦
¦ные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦сооружения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Основание ¦872,914¦1428,052¦ 941,114¦1734,574¦ ¦ ¦ ¦ ¦ ¦ 941,095¦897,795¦1416,067¦ ¦1632,094¦
¦из песка, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ПГС, щебня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Покрытие из ¦872,914¦1369,941¦1346,127¦1961,160¦ ¦ ¦ ¦ ¦ ¦1030,430¦966,875¦1380,832¦ ¦2546,063¦
¦асфальто- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦бетона ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Защитный ¦872,914¦1884,414¦1329,957¦1930,317¦ ¦ ¦ ¦ ¦ ¦1001,726¦947,310¦1375,613¦ ¦2653,750¦
¦слой из хо- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦лодных ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦асфальто- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦бетонных ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦смесей ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Поверхност- ¦872,914¦1365,474¦1306,419¦1930,128¦ ¦ ¦ ¦ ¦ ¦ 942,181¦917,195¦1380,987¦ ¦2090,583¦
¦ная обра- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ботка (с ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦применением ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦битума) ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Поверхност- ¦872,914¦1375,219¦1312,003¦1929,946¦ ¦ ¦ ¦ ¦ ¦ 954,460¦917,156¦1381,229¦ ¦2027,999¦
¦ная обра- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ботка (с ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦применением ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦битумной) ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Фрезерование¦872,914¦1462,034¦ 964,366¦1807,435¦ ¦ ¦ ¦ ¦ ¦ 952,038¦666,970¦1199,847¦ ¦1075,974¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Разметка ¦872,914¦1640,673¦1330,743¦1807,435¦ ¦ ¦ ¦ ¦ ¦ 968,716¦809,510¦1384,521¦ ¦1485,764¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Обстановка: ¦872,914¦1373,389¦1296,107¦1713,057¦ ¦ ¦ ¦ ¦ ¦ 952,671¦749,023¦1327,399¦ ¦1363,121¦
¦установка ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦знаков ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Обстановка: ¦872,914¦1369,919¦1296,303¦1723,751¦ ¦ ¦ ¦ ¦ ¦ 971,586¦728,097¦1375,496¦ ¦1495,994¦
¦прочие ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Барьерное ¦872,914¦1375,009¦1516,818¦1807,435¦ ¦ ¦ ¦ ¦ ¦ 997,081¦957,484¦1651,815¦ ¦2645,132¦
¦ограждение ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Работы на ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦мостах, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦в том числе:¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦ свайные ¦872,914¦1369,694¦1233,425¦1719,553¦ ¦ ¦ ¦ ¦ ¦ 939,903¦831,983¦1394,007¦ ¦1644,907¦
¦ работы, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ устройство ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ опор ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦ пролетные ¦872,914¦1340,659¦1316,254¦1711,080¦ ¦ ¦ ¦ ¦ ¦ 936,993¦898,903¦1468,240¦ ¦1995,099¦
¦ строения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦ мостовое ¦872,914¦1363,660¦1304,256¦1714,576¦ ¦ ¦ ¦ ¦ ¦ 946,332¦774,941¦1414,052¦ ¦1480,229¦
¦ полотно ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦ прочие ¦872,914¦1491,636¦1294,311¦1722,545¦ ¦ ¦ ¦ ¦ ¦ 968,618¦889,614¦1378,092¦ ¦1474,028¦
¦ работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+--------+
¦Содержание ¦872,914¦1426,402¦1077,229¦1728,498¦ ¦ ¦ ¦ ¦ ¦ 964,127¦709,401¦ ¦ ¦1299,901¦
¦автомобиль- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ных дорог ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦и мостов ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦------------+-------+--------+--------+--------+-------+------+------+------+------+--------+-------+--------+------+---------
Гродненская область (ОУП "Гроднооблдорстрой")
-------------+----------------------------------------------------------------------+----------------------------------------¬
¦Виды работ ¦Для расчета по ЕР-91 ¦Для расчета по ресурсно-сметным нормам ¦
¦ +----------------------------------------------------------------------+----------------------------------------+
¦ ¦Наименование затрат ¦Наименование затрат ¦
¦ +-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦ ¦Основ- ¦Эксплу- ¦Строи- ¦Транс- ¦Наклад-¦Плано-¦Вре- ¦Зимнее¦СМР ¦Наклад-¦Плано- ¦Времен- ¦Зимнее¦СМР ¦
¦ ¦ная ¦атация ¦тельные ¦портные ¦ные ¦вые ¦менные¦удоро-¦(спра-¦ные ¦вые ¦ные ¦удоро-¦(спра- ¦
¦ ¦зара- ¦машин и ¦матери- ¦затраты ¦расходы¦накоп-¦здания¦жание ¦вочно)¦расходы¦накоп- ¦здания и¦жание ¦вочно) ¦
¦ ¦ботная ¦меха- ¦алы ¦ ¦ ¦ления ¦и ¦ ¦ ¦ ¦ления ¦соору- ¦ ¦ ¦
¦ ¦плата ¦низмов ¦ ¦ ¦ ¦ ¦соору-¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦
¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Подготови- ¦872,914¦1517,719¦ 897,215¦1704,435¦ ¦ ¦ ¦ ¦ ¦943,201¦616,834¦1229,580¦ ¦ 930,943¦
¦тельные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Земляные ¦872,914¦1604,643¦ 966,082¦1702,827¦ ¦ ¦ ¦ ¦ ¦942,238¦653,990¦1311,933¦ ¦1226,311¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Укрепитель- ¦872,914¦1370,203¦1027,692¦1724,288¦ ¦ ¦ ¦ ¦ ¦926,632¦774,892¦1216,952¦ ¦1380,478¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦с камнем ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Укрепитель- ¦872,914¦1388,978¦1019,040¦1711,435¦ ¦ ¦ ¦ ¦ ¦934,352¦580,085¦1246,245¦ ¦ 885,133¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦без камня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Искусствен- ¦872,914¦1370,188¦1278,977¦1723,548¦ ¦ ¦ ¦ ¦ ¦977,646¦820,816¦1381,797¦ ¦1598,170¦
¦ные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦сооружения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Основание ¦872,914¦1380,531¦ 936,579¦1724,284¦ ¦ ¦ ¦ ¦ ¦988,481¦752,898¦1453,306¦ ¦1507,795¦
¦из песка, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ПГС, щебня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Покрытие из ¦872,914¦1389,705¦1339,974¦1941,128¦ ¦ ¦ ¦ ¦ ¦976,339¦987,737¦1389,243¦ ¦2657,027¦
¦асфальто- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦бетона ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Фрезерование¦872,914¦1469,400¦ 963,814¦1806,435¦ ¦ ¦ ¦ ¦ ¦922,476¦667,632¦1187,407¦ ¦1079,587¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Ремонт ¦872,914¦1375,007¦1200,667¦1725,233¦ ¦ ¦ ¦ ¦ ¦955,572¦750,059¦1274,720¦ ¦1740,169¦
¦покрытия ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Разметка ¦872,914¦1680,144¦1354,331¦1804,435¦ ¦ ¦ ¦ ¦ ¦961,358¦726,842¦1419,950¦ ¦1463,774¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Обстановка: ¦872,914¦1387,775¦1289,254¦1705,036¦ ¦ ¦ ¦ ¦ ¦953,929¦786,301¦1320,830¦ ¦1384,463¦
¦установка ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦знаков ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Обстановка: ¦872,914¦1361,939¦1282,593¦1730,955¦ ¦ ¦ ¦ ¦ ¦963,262¦709,263¦1337,473¦ ¦1409,797¦
¦прочие ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Барьерное ¦872,914¦1380,264¦1484,966¦1804,435¦ ¦ ¦ ¦ ¦ ¦993,649¦915,503¦1704,723¦ ¦2283,627¦
¦ограждение ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Работы на ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦мостах, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦в том числе:¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦ свайные ¦872,914¦1367,235¦1242,720¦1717,576¦ ¦ ¦ ¦ ¦ ¦998,705¦886,860¦1389,588¦ ¦1950,837¦
¦ работы, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ устройство ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ опор ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+------------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
Страницы: | Стр.1 | Стр.2 | Стр.3 | Стр.4 |
|