¦Искусствен-¦872,914¦1387,553¦1220,526¦1718,240¦ ¦ ¦ ¦ ¦ ¦943,948¦883,158¦1220,228¦ ¦1758,888¦
¦ные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦сооружения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+------+------+------+-------+-------+--------+------+--------+
¦Основание ¦872,914¦1384,165¦1353,686¦1750,939¦ ¦ ¦ ¦ ¦ ¦861,530¦735,972¦1235,919¦ ¦1780,161¦
¦из песка, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ПГС, щебня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+------+------+------+-------+-------+--------+------+--------+
¦Покрытие из¦872,914¦1383,250¦1339,757¦2305,661¦ ¦ ¦ ¦ ¦ ¦959,771¦864,993¦1296,653¦ ¦2587,259¦
¦асфальто- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦бетона ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+------+------+------+-------+-------+--------+------+--------+
¦Фрезерова- ¦872,914¦1423,549¦1008,450¦1677,593¦ ¦ ¦ ¦ ¦ ¦906,759¦827,417¦1248,920¦ ¦1186,745¦
¦ние ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+------+------+------+-------+-------+--------+------+--------+
¦Ремонт ¦872,914¦1390,349¦1352,114¦1745,114¦ ¦ ¦ ¦ ¦ ¦903,170¦846,016¦1247,201¦ ¦1637,221¦
¦покрытия ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+------+------+------+-------+-------+--------+------+--------+
¦Разметка ¦872,914¦1429,882¦1129,839¦1682,593¦ ¦ ¦ ¦ ¦ ¦953,052¦738,552¦1284,249¦ ¦1543,214¦
+-----------+-------+--------+--------+--------+-------+-------+------+------+------+-------+-------+--------+------+--------+
¦Обстановка:¦872,914¦1401,797¦1144,267¦1650,057¦ ¦ ¦ ¦ ¦ ¦862,882¦772,224¦1243,947¦ ¦1519,093¦
¦установка ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦знаков ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+------+------+------+-------+-------+--------+------+--------+
¦Обстановка:¦872,914¦1395,729¦1213,930¦1682,150¦ ¦ ¦ ¦ ¦ ¦825,779¦785,316¦1073,004¦ ¦1320,360¦
¦прочие ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+------+------+------+-------+-------+--------+------+--------+
¦Барьерное ¦872,914¦1419,100¦1192,548¦1682,593¦ ¦ ¦ ¦ ¦ ¦954,546¦915,982¦1198,866¦ ¦2580,671¦
¦ограждение ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+------+------+------+-------+-------+--------+------+--------+
¦Работы на ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦мостах, в ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦том числе: ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+------+------+------+-------+-------+--------+------+--------+
¦ мостовое ¦872,914¦1393,633¦1220,530¦1658,763¦ ¦ ¦ ¦ ¦ ¦940,566¦841,284¦1176,018¦ ¦1478,824¦
¦ полотно ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+------+------+------+-------+-------+--------+------+--------+
¦ прочие ¦872,914¦1416,093¦1226,442¦1678,383¦ ¦ ¦ ¦ ¦ ¦852,502¦747,467¦1157,350¦ ¦1238,976¦
¦ работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+------+------+------+-------+-------+--------+------+--------+
¦Содержание ¦872,914¦1364,214¦1204,594¦1656,221¦ ¦ ¦ ¦ ¦ ¦767,671¦579,951¦ ¦ ¦1156,409¦
¦автомо- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦бильных ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦дорог и ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦мостов ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦-----------+-------+--------+--------+--------+-------+-------+------+------+------+-------+-------+--------+------+---------
Минская область (РУП "Минскавтодор-центр")
------------+----------------------------------------------------------------------+----------------------------------------¬
¦Виды работ ¦Для расчета по ЕР-91 ¦Для расчета по ресурсно-сметным нормам ¦
¦ +----------------------------------------------------------------------+----------------------------------------+
¦ ¦Наименование затрат ¦Наименование затрат ¦
¦ +-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦ ¦Основ- ¦Эксплу- ¦Строи- ¦Транс- ¦Наклад-¦Плано-¦Вре- ¦Зимнее¦СМР ¦Наклад-¦Плано- ¦Времен- ¦Зимнее¦СМР ¦
¦ ¦ная ¦атация ¦тельные ¦портные ¦ные ¦вые ¦менные¦удоро-¦(спра-¦ные ¦вые ¦ные ¦удоро-¦(спра- ¦
¦ ¦зара- ¦машин и ¦матери- ¦затраты ¦расходы¦накоп-¦здания¦жание ¦вочно)¦расходы¦накоп- ¦здания и¦жание ¦вочно) ¦
¦ ¦ботная ¦меха- ¦алы ¦ ¦ ¦ления ¦и ¦ ¦ ¦ ¦ления ¦соору- ¦ ¦ ¦
¦ ¦плата ¦низмов ¦ ¦ ¦ ¦ ¦соору-¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦
¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Подготови- ¦872,914¦1396,309¦1017,568¦1686,801¦ ¦ ¦ ¦ ¦ ¦941,015¦713,091¦1184,250¦ ¦1036,331¦
¦тельные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Земляные ¦872,914¦1405,497¦1030,438¦1730,788¦ ¦ ¦ ¦ ¦ ¦867,313¦774,703¦1205,131¦ ¦1201,072¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Укрепитель-¦872,914¦1380,589¦1114,902¦1656,919¦ ¦ ¦ ¦ ¦ ¦883,008¦719,367¦1150,663¦ ¦1320,804¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦с камнем ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Укрепитель-¦872,914¦1378,333¦1026,792¦1648,446¦ ¦ ¦ ¦ ¦ ¦883,277¦723,444¦1150,728¦ ¦1084,662¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦без камня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Искусствен-¦872,914¦1399,533¦1225,278¦1720,423¦ ¦ ¦ ¦ ¦ ¦872,986¦796,769¦1275,735¦ ¦1756,455¦
¦ные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦сооружения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Основание ¦872,914¦1403,526¦1368,005¦1712,051¦ ¦ ¦ ¦ ¦ ¦872,282¦783,603¦1206,801¦ ¦1646,674¦
¦из песка, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ПГС, щебня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Покрытие из¦872,914¦1380,358¦1325,281¦2297,729¦ ¦ ¦ ¦ ¦ ¦974,885¦989,694¦1248,716¦ ¦2559,375¦
¦асфальто- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦бетона ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Фрезерова- ¦872,914¦1447,328¦ 998,455¦1679,696¦ ¦ ¦ ¦ ¦ ¦981,534¦778,087¦1265,672¦ ¦1347,327¦
¦ние ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Ремонт ¦872,914¦1389,919¦1368,838¦1706,682¦ ¦ ¦ ¦ ¦ ¦925,179¦835,891¦1283,971¦ ¦1650,296¦
¦покрытия ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Разметка ¦872,914¦1376,477¦1138,971¦1677,862¦ ¦ ¦ ¦ ¦ ¦802,058¦761,439¦1269,689¦ ¦1550,996¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Обстановка:¦872,914¦1385,786¦1082,255¦1686,221¦ ¦ ¦ ¦ ¦ ¦851,908¦763,606¦1195,597¦ ¦1453,177¦
¦установка ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦знаков ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Обстановка:¦872,914¦1423,474¦1247,824¦1701,299¦ ¦ ¦ ¦ ¦ ¦864,175¦794,689¦1165,073¦ ¦1420,646¦
¦прочие ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Барьерное ¦872,914¦1436,615¦1194,073¦1696,357¦ ¦ ¦ ¦ ¦ ¦931,984¦918,550¦1177,997¦ ¦2672,514¦
¦ограждение ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Работы на ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦мостах, в ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦том числе: ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦ свайные ¦872,914¦1390,792¦1304,584¦1693,903¦ ¦ ¦ ¦ ¦ ¦867,912¦785,741¦1258,113¦ ¦1388,961¦
¦ работы, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ устройство¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ опор ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦ пролетные ¦872,914¦1394,590¦1318,916¦1731,045¦ ¦ ¦ ¦ ¦ ¦856,946¦783,910¦1192,897¦ ¦1347,324¦
¦ строения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦ мостовое ¦872,914¦1462,469¦1434,226¦1627,857¦ ¦ ¦ ¦ ¦ ¦818,338¦732,659¦1190,789¦ ¦1396,063¦
¦ полотно ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦ гидроизо- ¦872,914¦1375,690¦1323,691¦1677,861¦ ¦ ¦ ¦ ¦ ¦897,910¦783,480¦1083,636¦ ¦1321,710¦
¦ ляция ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦ прочие ¦872,914¦1458,050¦1284,474¦1685,069¦ ¦ ¦ ¦ ¦ ¦860,325¦784,331¦1268,627¦ ¦1318,817¦
¦ работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+--------+
¦Содержание ¦872,914¦1484,341¦1011,244¦1644,667¦ ¦ ¦ ¦ ¦ ¦818,664¦710,654¦ ¦ ¦1126,384¦
¦автомо- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦бильных ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦дорог и ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦мостов ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦-----------+-------+--------+--------+--------+-------+------+------+------+------+-------+-------+--------+------+---------
Минская область (УП "Минскоблдорстрой")
------------+-----------------------------------------------------------------------------+----------------------------------------¬
¦Виды работ ¦Для расчета по ЕР-91 ¦Для расчета по ресурсно-сметным нормам ¦
¦ +-----------------------------------------------------------------------------+----------------------------------------+
¦ ¦Наименование затрат ¦Наименование затрат ¦
¦ +-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ ¦Основ- ¦Эксплу- ¦Строи- ¦Транс- ¦Наклад-¦Плано- ¦Времен- ¦Зимнее ¦СМР ¦Наклад-¦Плано- ¦Времен- ¦Зимнее¦СМР ¦
¦ ¦ная ¦атация ¦тельные ¦портные ¦ные ¦вые ¦ные ¦удоро- ¦(спра- ¦ные ¦вые ¦ные ¦удоро-¦(спра- ¦
¦ ¦зара- ¦машин и ¦матери- ¦затраты ¦расходы¦накоп- ¦здания и¦жание ¦вочно) ¦расходы¦накоп- ¦здания и¦жание ¦вочно) ¦
¦ ¦ботная ¦меха- ¦алы ¦ ¦ ¦ления ¦соору- ¦ ¦ ¦ ¦ления ¦соору- ¦ ¦ ¦
¦ ¦плата ¦низмов ¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Подготови- ¦872,914¦1354,821¦1038,036¦1645,478¦575,983¦509,041¦1291,838¦1107,035¦ 884,936¦795,960¦637,744¦1215,661¦ ¦ 933,599¦
¦тельные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Земляные ¦872,914¦1417,623¦1049,782¦1706,131¦747,663¦529,518¦1374,669¦1123,783¦1046,987¦844,823¦822,303¦1235,898¦ ¦1160,147¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Укрепитель-¦872,914¦1380,903¦1072,057¦1704,783¦723,556¦564,421¦1129,226¦1109,291¦1196,420¦813,445¦808,095¦1120,034¦ ¦1281,159¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦с камнем ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Укрепитель-¦872,914¦1377,855¦1046,102¦1640,448¦693,681¦612,717¦1177,272¦1107,518¦1025,145¦697,373¦688,776¦1181,103¦ ¦ 933,858¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦без камня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Искусствен-¦872,914¦1386,152¦1264,044¦1684,474¦837,494¦799,991¦1287,722¦1248,052¦1493,813¦871,130¦854,501¦1238,925¦ ¦1608,037¦
¦ные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦сооружения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Основание ¦872,914¦1434,682¦1147,969¦1707,692¦858,428¦720,762¦1204,792¦1208,750¦1600,885¦880,204¦841,824¦1197,792¦ ¦1622,178¦
¦из песка, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ПГС, щебня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Покрытие из¦872,914¦1400,716¦1208,696¦1734,638¦ ¦ ¦ ¦ ¦ ¦865,655¦838,838¦1140,848¦ ¦2169,783¦
¦гравийно- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦эмульсион- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ной смеси ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Покрытие из¦872,914¦1381,157¦1224,285¦2230,681¦868,980¦817,272¦1210,011¦1047,351¦2558,076¦887,921¦975,335¦1205,615¦ ¦2608,344¦
¦асфальто- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦бетона ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Ремонт ¦872,914¦1404,823¦1214,293¦1720,606¦792,505¦784,160¦1147,450¦1100,048¦1767,648¦813,700¦814,486¦1140,916¦ ¦1818,181¦
¦покрытия ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Разметка ¦872,914¦1384,931¦1130,646¦1680,593¦ ¦ ¦ ¦ ¦ ¦943,328¦737,689¦1274,790¦ ¦1576,256¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Обстановка:¦872,914¦1392,730¦1133,961¦1648,505¦856,955¦848,691¦1224,850¦1247,666¦1568,721¦866,990¦853,394¦1217,167¦ ¦1559,871¦
¦установка ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦знаков ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Обстановка:¦872,914¦1385,807¦1248,240¦1699,227¦842,776¦793,708¦1218,701¦1065,797¦1357,895¦873,069¦836,701¦1215,347¦ ¦1440,795¦
¦прочие ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Барьерное ¦872,914¦1381,388¦1515,769¦1697,791¦818,334¦802,274¦1194,502¦1173,421¦2124,725¦843,956¦887,749¦1174,587¦ ¦2310,672¦
¦ограждение ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Работы на ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦мостах, в ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦том числе: ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ свайные ¦872,914¦1415,123¦1267,268¦1691,925¦793,216¦623,735¦1257,738¦1170,156¦1330,624¦871,793¦849,363¦1238,859¦ ¦1346,075¦
¦ работы, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ устройство¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ опор ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ пролетные ¦872,914¦1367,220¦1323,544¦1715,033¦813,159¦635,882¦1302,279¦1337,556¦1281,680¦840,470¦847,570¦1253,666¦ ¦1287,238¦
¦ строения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ мостовое ¦872,914¦1423,759¦1200,541¦1698,904¦800,517¦693,221¦1238,704¦1235,270¦1349,964¦833,000¦771,007¦1199,533¦ ¦1331,320¦
¦ полотно ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ прочие ¦872,914¦1385,013¦1357,480¦1658,293¦808,878¦601,221¦1264,666¦1230,793¦1319,487¦866,542¦711,377¦1109,578¦ ¦1237,514¦
¦ работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Содержание ¦872,914¦1384,374¦1237,364¦1628,641¦ ¦ ¦ ¦ ¦ ¦793,897¦633,132¦ ¦ ¦1090,354¦
¦автомо- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦бильных ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦дорог и ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦мостов ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+---------
Могилевская область (РУП "Могилевавтодор")
------------+-----------------------------------------------------------------------------+----------------------------------------¬
¦Виды работ ¦Для расчета по ЕР-91 ¦Для расчета по ресурсно-сметным нормам ¦
¦ +-----------------------------------------------------------------------------+----------------------------------------+
¦ ¦Наименование затрат ¦Наименование затрат ¦
¦ +-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ ¦Основ- ¦Эксплу- ¦Строи- ¦Транс- ¦Наклад-¦Плано- ¦Времен- ¦Зимнее ¦СМР ¦Наклад-¦Плано- ¦Времен- ¦Зимнее¦СМР ¦
¦ ¦ная ¦атация ¦тельные ¦портные ¦ные ¦вые ¦ные ¦удоро- ¦(спра- ¦ные ¦вые ¦ные ¦удоро-¦(спра- ¦
¦ ¦зара- ¦машин и ¦матери- ¦затраты ¦расходы¦накоп- ¦здания и¦жание ¦вочно) ¦расходы¦накоп- ¦здания и¦жание ¦вочно) ¦
¦ ¦ботная ¦меха- ¦алы ¦ ¦ ¦ления ¦соору- ¦ ¦ ¦ ¦ления ¦соору- ¦ ¦ ¦
¦ ¦плата ¦низмов ¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Подготови- ¦872,914¦1442,177¦1031,075¦1504,241¦ ¦ ¦ ¦ ¦ ¦799,835¦707,418¦1121,168¦ ¦ 952,993¦
¦тельные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Земляные ¦872,914¦1705,231¦1197,828¦1607,254¦815,563¦726,799¦1279,596¦1188,783¦1281,565¦821,463¦820,410¦1279,490¦ ¦1331,871¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Укрепитель-¦872,914¦1378,294¦1248,452¦1582,030¦ ¦ ¦ ¦ ¦ ¦856,763¦763,013¦1287,730¦ ¦1395,966¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦с камнем ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Укрепитель-¦872,914¦1312,716¦1170,554¦1552,241¦ ¦ ¦ ¦ ¦ ¦691,554¦568,841¦1167,728¦ ¦ 890,873¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦без камня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Искусствен-¦872,914¦1386,252¦1293,178¦1614,474¦862,239¦653,581¦1281,713¦1351,971¦1795,172¦867,953¦656,738¦1281,229¦ ¦1756,072¦
¦ные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦сооружения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Основание ¦872,914¦1420,112¦1373,424¦1817,452¦859,757¦732,392¦1398,835¦1379,114¦1791,679¦871,158¦745,186¦1396,446¦ ¦1679,117¦
¦из песка, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ПГС, щебня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Покрытие из¦872,914¦1387,164¦1324,542¦1817,952¦772,284¦688,425¦1440,785¦1337,755¦2768,917¦803,536¦799,033¦1340,959¦ ¦2821,968¦
¦асфальто- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦бетона ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Фрезерова- ¦872,914¦1446,603¦1131,807¦1637,241¦ ¦ ¦ ¦ ¦ ¦773,553¦642,851¦1317,689¦ ¦1294,343¦
¦ние ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Разметка ¦872,914¦1322,291¦1092,806¦1549,241¦ ¦ ¦ ¦ ¦ ¦780,715¦772,009¦1338,751¦ ¦1658,054¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Обстановка:¦872,914¦1399,127¦1103,946¦1554,210¦ ¦ ¦ ¦ ¦ ¦720,242¦619,456¦1442,532¦ ¦1731,004¦
¦установка ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦знаков ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Обстановка:¦872,914¦1395,403¦1101,795¦1512,279¦744,962¦628,812¦1265,214¦1169,169¦1592,524¦754,190¦641,188¦1261,597¦ ¦1670,942¦
¦прочие ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Барьерное ¦872,914¦1404,461¦1123,971¦1553,471¦ ¦ ¦ ¦ ¦ ¦730,306¦667,523¦1360,627¦ ¦2536,827¦
¦ограждение ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Работы на ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦мостах, в ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦том числе: ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ свайные ¦872,914¦1344,426¦1298,712¦1575,619¦ ¦ ¦ ¦ ¦ ¦845,887¦644,309¦1334,628¦ ¦1477,748¦
¦ работы, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ устройство¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ опор ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ пролетные ¦872,914¦1366,508¦1292,936¦1604,259¦ ¦ ¦ ¦ ¦ ¦827,948¦672,167¦1298,558¦ ¦1533,341¦
¦ строения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ мостовое ¦872,914¦1369,779¦1161,493¦1576,041¦ ¦ ¦ ¦ ¦ ¦886,036¦719,488¦1299,672¦ ¦1590,103¦
¦ полотно ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ прочие ¦872,914¦1457,435¦1056,106¦1558,155¦ ¦ ¦ ¦ ¦ ¦838,944¦675,169¦1391,576¦ ¦1223,405¦
¦ работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Содержание ¦872,914¦1397,191¦1055,879¦1549,687¦ ¦ ¦ ¦ ¦ ¦839,815¦677,139¦ ¦ ¦1143,528¦
¦автомо- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦бильных ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦дорог и ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦мостов ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+---------
Могилевская область (УКДПРСП "Могилевоблдорстрой")
------------+-----------------------------------------------------------------------------+----------------------------------------¬
¦Виды работ ¦Для расчета по ЕР-91 ¦Для расчета по ресурсно-сметным нормам ¦
¦ +-----------------------------------------------------------------------------+----------------------------------------+
¦ ¦Наименование затрат ¦Наименование затрат ¦
¦ +-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ ¦Основ- ¦Эксплу- ¦Строи- ¦Транс- ¦Наклад-¦Плано- ¦Времен- ¦Зимнее ¦СМР ¦Наклад-¦Плано- ¦Времен- ¦Зимнее¦СМР ¦
¦ ¦ная ¦атация ¦тельные ¦портные ¦ные ¦вые ¦ные ¦удоро- ¦(спра- ¦ные ¦вые ¦ные ¦удоро-¦(спра- ¦
¦ ¦зара- ¦машин и ¦матери- ¦затраты ¦расходы¦накоп- ¦здания и¦жание ¦вочно) ¦расходы¦накоп- ¦здания и¦жание ¦вочно) ¦
¦ ¦ботная ¦меха- ¦алы ¦ ¦ ¦ления ¦соору- ¦ ¦ ¦ ¦ления ¦соору- ¦ ¦ ¦
¦ ¦плата ¦низмов ¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦ ¦ ¦жения ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Подготови- ¦872,914¦1315,012¦1007,439¦1508,549¦756,499¦686,943¦1159,142¦1010,010¦ 815,065¦826,065¦765,258¦1157,873¦ ¦ 969,279¦
¦тельные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Земляные ¦872,914¦1494,963¦1031,354¦1705,429¦850,551¦541,655¦1142,130¦1138,049¦1115,541¦878,456¦762,222¦1134,976¦ ¦1220,611¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Укрепитель-¦872,914¦1448,401¦1184,982¦1543,516¦814,429¦719,358¦1262,185¦1655,071¦1573,789¦842,087¦751,046¦1257,696¦ ¦1471,890¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦с камнем ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Укрепитель-¦872,914¦1341,687¦1051,476¦1534,241¦597,822¦513,324¦1143,862¦1095,665¦ 974,453¦619,862¦530,540¦1081,665¦ ¦ 966,959¦
¦ные работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦без камня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Искусствен-¦872,914¦1419,811¦1254,143¦1612,677¦783,774¦639,221¦1316,364¦1211,253¦1629,047¦892,427¦740,199¦1312,343¦ ¦1493,498¦
¦ные ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦сооружения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Основание ¦872,914¦1404,272¦1128,611¦1629,047¦855,820¦633,298¦1358,006¦1399,292¦1687,028¦906,631¦791,774¦1349,481¦ ¦1747,210¦
¦из песка, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ПГС, щебня ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Покрытие из¦872,914¦1385,478¦1311,505¦1827,166¦784,346¦696,457¦1350,447¦1242,779¦2611,144¦912,163¦872,551¦1349,502¦ ¦2781,224¦
¦асфальто- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦бетона ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Фрезерова- ¦872,914¦1435,655¦1126,551¦1613,241¦ ¦ ¦ ¦ ¦ ¦765,146¦669,111¦1297,598¦ ¦1137,010¦
¦ние ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Разметка ¦872,914¦1303,279¦1084,703¦1504,627¦ ¦ ¦ ¦ ¦ ¦727,184¦723,261¦1226,489¦ ¦1509,001¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Обстановка:¦872,914¦1415,058¦1105,316¦1512,374¦703,259¦624,867¦1250,361¦1235,746¦1602,636¦769,874¦676,883¦1238,685¦ ¦1641,126¦
¦установка ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦знаков ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Обстановка:¦872,914¦1391,197¦1098,727¦1498,617¦ ¦ ¦ ¦ ¦ ¦778,172¦671,240¦1242,561¦ ¦1557,245¦
¦прочие ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Барьерное ¦872,914¦1412,566¦1120,055¦1562,241¦ ¦ ¦ ¦ ¦ ¦736,628¦664,092¦1371,269¦ ¦2231,408¦
¦ограждение ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Работы на ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦мостах, в ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦том числе: ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ свайные ¦872,914¦1434,815¦1270,296¦1577,812¦ ¦ ¦ ¦ ¦ ¦939,515¦877,708¦1447,553¦ ¦1340,066¦
¦ работы, ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ устройство¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦ опор ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ пролетные ¦872,914¦1352,213¦1281,551¦1584,724¦ ¦ ¦ ¦ ¦ ¦810,278¦653,601¦1236,390¦ ¦1498,246¦
¦ строения ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ мостовое ¦872,914¦1391,448¦1141,094¦1554,830¦ ¦ ¦ ¦ ¦ ¦814,183¦735,781¦1245,171¦ ¦1554,095¦
¦ полотно ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦ прочие ¦872,914¦1441,654¦1069,938¦1528,515¦ ¦ ¦ ¦ ¦ ¦913,207¦777,055¦1438,314¦ ¦1399,302¦
¦ работы ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
+-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+--------+
¦Содержание ¦872,914¦1400,437¦ 959,446¦1547,483¦ ¦ ¦ ¦ ¦ ¦887,334¦619,737¦ ¦ ¦1150,831¦
¦автомо- ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦бильных ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦дорог и ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦мостов ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦
¦-----------+-------+--------+--------+--------+-------+-------+--------+--------+--------+-------+-------+--------+------+---------
Приложение 2
к приказу Министерства
транспорта и коммуникаций
Республики Беларусь
26.10.2005 N 10-Д
ИНДЕКСЫ ИЗМЕНЕНИЯ СТОИМОСТИ ЗАТРАТ НА СОДЕРЖАНИЕ ЕДИНОГО
ЗАКАЗЧИКА (ЗАСТРОЙЩИКА) И ДИРЕКЦИИ СТРОЯЩЕГОСЯ ПРЕДПРИЯТИЯ
ОКТЯБРЬ 2005 ГОДА
------------+-------------------------------------------------------¬
¦Регионы ¦Индексы изменения стоимости затрат ¦
¦ +---------------------------+---------------------------+
¦ ¦на содержание единого ¦на содержание дирекции ¦
¦ ¦заказчика (застройщика) ¦строящегося предприятия ¦
¦ +-------------+-------------+-------------+-------------+
¦ ¦Для объектов,¦Для объектов,¦Для объектов,¦Для объектов,¦
¦ ¦освобождаемых¦не освобож- ¦освобождаемых¦не освобож- ¦
¦ ¦от налога на ¦даемых от ¦от налога на ¦даемых от ¦
¦ ¦добавленную ¦налога на ¦добавленную ¦налога на ¦
¦ ¦стоимость ¦добавленную ¦стоимость ¦добавленную ¦
¦ ¦ ¦стоимость ¦ ¦стоимость ¦
+-----------+-------------+-------------+-------------+-------------+
¦Брестская ¦ 1191,515 ¦ 1112,404 ¦ 1178,046 ¦ 1107,395 ¦
¦область ¦ ¦ ¦ ¦ ¦
+-----------+-------------+-------------+-------------+-------------+
¦Витебская ¦ 1189,625 ¦ 1109,592 ¦ 1190,410 ¦ 1118,690 ¦
¦область ¦ ¦ ¦ ¦ ¦
+-----------+-------------+-------------+-------------+-------------+
¦Гомельская ¦ 1190,479 ¦ 1109,428 ¦ 1182,569 ¦ 1110,406 ¦
¦область ¦ ¦ ¦ ¦ ¦
+-----------+-------------+-------------+-------------+-------------+
¦Гродненская¦ 1172,643 ¦ 1102,713 ¦ 1150,266 ¦ 1085,926 ¦
¦область ¦ ¦ ¦ ¦ ¦
+-----------+-------------+-------------+-------------+-------------+
¦Минская ¦ 1219,072 ¦ 1132,693 ¦ 1202,391 ¦ 1124,166 ¦
¦область ¦ ¦ ¦ ¦ ¦
+-----------+-------------+-------------+-------------+-------------+
¦Могилевская¦ 1160,125 ¦ 1080,796 ¦ 1139,432 ¦ 1068,257 ¦
¦область ¦ ¦ ¦ ¦ ¦
+-----------+-------------+-------------+-------------+-------------+
¦г.Минск ¦ 1156,191 ¦ 1078,648 ¦ 1126,874 ¦ 1058,633 ¦
¦(без КПД) ¦ ¦ ¦ ¦ ¦
+-----------+-------------+-------------+-------------+-------------+
¦г.Минск ¦ 1165,221 ¦ - ¦ 1136,441 ¦ - ¦
¦(с КПД) ¦ ¦ ¦ ¦ ¦
¦-----------+-------------+-------------+-------------+--------------